Home / Environment / Shetland Windfarm Paid Millions to Stay Idle

Shetland Windfarm Paid Millions to Stay Idle

Summary

  • Viking windfarm receives up to £10 million annually for shutdown.
  • Locals face high energy bills despite nearby windfarm.
  • Grid capacity issues cause turbines to be turned off frequently.
Shetland Windfarm Paid Millions to Stay Idle

The Viking windfarm in Shetland, operational since September 2024, receives substantial payments to cease operations during high winds. In 2025, operators SSE Renewables were compensated £9.86 million, part of an annual sum reaching up to £10 million, because the local grid lacks the capacity to transmit the generated power. Consequently, turbines were stationary for about 65% of their potential operating time that year.

This situation leads to a stark contrast for Shetland residents, who face some of the UK's highest energy bills despite the presence of the £580 million windfarm. They rely on less efficient diesel and gas power stations, while the subsea cable connecting the windfarm to the mainland grid remains underutilized for local supply. This inefficiency adds to the overall cost burden on households across Britain.

These constraint payments, designed to compensate operators for not generating power, amounted to over £445 million nationwide between January 1, 2025, and April 17, 2026. The Viking windfarm itself received £13.5 million in such payments over this period. Ultimately, these costs are reflected in escalating consumer energy bills, prompting criticism from local communities and politicians about the financial impact and lack of local benefit.

Disclaimer: This story has been auto-aggregated and auto-summarised by a computer program. This story has not been edited or created by the Feedzop team.

Read more news on

Property Code: 5571