Home / Environment / Long Beach Battles Ocean's Fury with Dredging Project

Long Beach Battles Ocean's Fury with Dredging Project

Summary

  • Coastal protection project aims to restore Long Beach Peninsula after storms.
  • Dredging will add 415,000 cubic yards of sand to replenish beaches.
  • The $11.4 million project is scheduled for completion in February 2027.
Long Beach Battles Ocean's Fury with Dredging Project

Long Beach is actively engaged in a significant coastal rehabilitation effort to shield its Peninsula from the impacts of recent severe storms. An $11.4 million project, encompassing the Alamitos Bay Entrance Dredging Project, is now underway to fortify the area. This initiative plans to deepen the bay entrance, restoring critical navigational depths that have not been addressed in over two decades.

The project's dredged material will be strategically reused to enhance Peninsula Beach. Approximately 415,000 cubic yards of sand are expected to be deposited, widening the shoreline by up to 200 feet. This expansion is designed to create a more robust buffer zone, offering greater protection for homes and infrastructure against ocean surges.

Residents express mixed sentiments, with some welcoming the protective measures while others remain concerned about the ocean's persistent power. The dredging and sand replenishment are scheduled to conclude in February 2027, as the city prepares for potential future storm seasons and king tides.