Kendal Flood Defences: Decade On, Still Vulnerable
21 Oct
Summary
- Kendal's flood defences are far from complete, nearly 11 years post-Storm Desmond.
- The flood management scheme's cost has nearly doubled to £130 million.
- Carlisle is developing a community resilience plan for emergencies.
Nearly 11 years after Storm Desmond, residents of Kendal express ongoing vulnerability due to incomplete flood defences. The Kendal Flood Risk Management Scheme, initiated in 2021 and initially slated for completion in 2025, now faces a revised completion date of 2028 for its town centre components. The project's budget has nearly doubled from its original £76 million to an estimated £130 million.
The Environment Agency reports that town centre defences are 70% complete, with essential flood gates and pumps prepared for potential winter use. However, community members like Lis Dales, who established a flood action group after her home was inundated in 2015, believe current measures offer minimal additional protection. The delayed completion leaves residents feeling insecure about future flooding events.
In parallel, efforts are underway in Carlisle to enhance community preparedness. The Botcherby Community Centre, in collaboration with the Environment Agency and local councils, is instrumental in developing the Carlisle Community Resilience Plan. This initiative aims to create a structured, city-wide approach to managing emergencies, incorporating resident input to address future shocks effectively.