Home / Environment / Corpus Christi Water Woes: Groundwater Project in Jeopardy
Corpus Christi Water Woes: Groundwater Project in Jeopardy
16 Jul
Summary
- Evangeline project faces delays, potential cancellation due to Sinton's opposition.
- Desalination commitment is key to reaching an agreement with Sinton.
- City has already invested $66 million, with total project cost estimated at $665 million.

The Evangeline groundwater project for Corpus Christi is facing significant delays, with its operational start postponed from the end of the year and its overall completion now in question. This uncertainty stems from opposition by the city of Sinton, which relies on the same aquifer and fears the project will compromise its water quality and availability.
Negotiations between Corpus Christi and Sinton are ongoing, with Sinton's city manager stating that a resolution depends on Corpus Christi's commitment to developing desalination. The city has already spent $66 million, with the total project estimated at $665 million. A failure to reach an agreement could lead to a lengthy legal battle, potentially delaying the project for years.
Corpus Christi officials view the Evangeline project as vital for diversifying its water supply, which is currently vulnerable to drought. However, some city council members are questioning the continued investment given the project's financial burdens and stalled progress. The city has set a tight deadline, with a decision on whether to continue investing potentially coming in the next few weeks.
Several desalination initiatives are being considered by Corpus Christi, including proposals involving Corpus Christi Polymers and a facility on Harbor Island, but none are finalized. The city also has a reservation for desalinated water from the Nueces River Authority, though this project faces scrutiny. Sinton's concerns are linked to Corpus Christi's progress on desalination, with Sinton's city manager expressing skepticism about the Inner Harbor project's approval after a recent federal grant application denial.
Despite spring rains easing immediate drought concerns, Corpus Christi's primary water sources remain critically low, filled to only 15.7% capacity as of July 13. The projected water emergency timeline has been pushed back to September 2027. City officials emphasize that without the Evangeline project's 24 million gallons per day, there are few other options available in the short term, highlighting the urgency of the ongoing discussions.