Home / Business and Economy / Cranleigh Leisure Centre Cost Nearly Doubles
Cranleigh Leisure Centre Cost Nearly Doubles
30 Jun
Summary
- Leisure centre project cost nearly doubled since announcement.
- Initial £20m cost increased to nearly £36m.
- Work on the new centre has not yet started; completion due in 2027.

Councillors are scheduled to meet this Tuesday evening to receive updates on the new Cranleigh Leisure Centre. The project's cost has significantly increased, nearly doubling from its initial announcement.
Plans initially revealed in March 2025 outlined a facility with a six-lane swimming pool, teaching pool, gym, studios, and a cafe. The estimated cost then was £20m, but a revised budget of almost £36m was set by the council in December. Work on the new centre has not yet begun, with an anticipated completion date in 2027.
Opposition councillors highlight ongoing concerns from residents regarding project delays, construction disruption, and practical issues like parking and access. The current leisure centre, which is 55 years old and has "exceeded its life expectancy," will be demolished upon the completion of the new facility. Community members acknowledge the need for improvement but stress the importance of incorporating adequate parking into the new design.