feedzop-word-mark-logo
searchLogin
Feedzop
homeFor YouUnited StatesUnited States
You
bookmarksYour BookmarkshashtagYour Topics
Trending
trending

Nick Reiner killed his parents

trending

Snow causes school delays

trending

Fallout Season 2 release earlier

trending

Sydney Sweeney TikTok hate

trending

SBI cuts FD interest rates

trending

Arizona revokes Underdog's license

trending

New flu variant spreads

trending

High wind warning issued

trending

PA Lottery winning tickets sold

Terms of UsePrivacy PolicyAboutJobsPartner With Us

© 2025 Advergame Technologies Pvt. Ltd. ("ATPL"). Gamezop ® & Quizzop ® are registered trademarks of ATPL.

Gamezop is a plug-and-play gaming platform that any app or website can integrate to bring casual gaming for its users. Gamezop also operates Quizzop, a quizzing platform, that digital products can add as a trivia section.

Over 5,000 products from more than 70 countries have integrated Gamezop and Quizzop. These include Amazon, Samsung Internet, Snap, Tata Play, AccuWeather, Paytm, Gulf News, and Branch.

Games and trivia increase user engagement significantly within all kinds of apps and websites, besides opening a new stream of advertising revenue. Gamezop and Quizzop take 30 minutes to integrate and can be used for free: both by the products integrating them and end users

Increase ad revenue and engagement on your app / website with games, quizzes, astrology, and cricket content. Visit: business.gamezop.com

Property Code: 5571

Home / Business and Economy / Coal India Misses Solar Target: Only 4% Capacity Installed

Coal India Misses Solar Target: Only 4% Capacity Installed

16 Dec

•

Summary

  • Coal India installed 4.08% of its 3,000 MW solar target by December 2024.
  • CAG urged faster execution for Coal India to achieve Net Zero energy status.
  • Project completion is now extended to 2027-28, with work orders for 727 MW.
Coal India Misses Solar Target: Only 4% Capacity Installed

The Comptroller and Auditor General of India (CAG) has reported that Coal India Ltd (CIL) has fallen far short of its 3,000 MW solar power generation target, having installed only 4.08% of the capacity by December 2024. This significant delay has prompted the CAG to urge CIL to expedite project development to achieve its Net Zero energy company goals.

Despite being entrusted with the target in 2017 for completion by 2024, CIL has only progressed with work orders for 692.50 MW of ground-mounted and 34.56 MW of rooftop solar projects. The projected commissioning for these projects has been extended to the 2027-28 fiscal year, indicating a substantial setback from the original timeline.

To facilitate this transition, Coal India had established joint ventures with NTPC Ltd and NLC India Limited for 1000 MW projects each, alongside a Memorandum of Understanding with Solar Energy Corporation Ltd. A dedicated special purpose vehicle, CIL Navikarniya Urja Ltd, was also formed to fast-track solar initiatives.

Disclaimer: This story has been auto-aggregated and auto-summarised by a computer program. This story has not been edited or created by the Feedzop team.
Coal India was tasked with developing 3,000 MW of solar power.
CAG is auditing Coal India due to significant delays in achieving its solar power generation targets and for progress towards becoming a Net Zero energy company.
The completion of Coal India's solar projects has been extended and is now anticipated by the 2027-28 fiscal year.

Read more news on

Business and Economyside-arrow

You may also like

SEBI Clears Adani Kin in Insider Trading Case

13 Dec • 26 reads

article image

NTPC Unit Powers Up in Gujarat

10 Dec • 43 reads

article image

India's Green Grid: Transmission Woes Hamper Renewables

1 Dec • 73 reads

article image

NTPC Green Energy Lock-In Ends: 69% Shares to Float

26 Nov • 101 reads

article image

Ceigall India Lands Major ₹58.5 Cr Annual Substation Deal

24 Nov • 104 reads

article image