NGT Dismisses Sand Mining Appeal Over Delay
28 Dec, 2025
Summary
- NGT dismissed an appeal challenging sand mining clearance cancellation.
- Appeal filed 178 days after cancellation, exceeding the 90-day limit.
- Appellant falsely claimed non-receipt of cancellation orders.

The National Green Tribunal's Principal Bench in New Delhi has rejected an appeal against the revocation of environmental clearance for sand mining operations along the Dhasan river in Jhansi district. The tribunal determined that the appeal was filed 178 days after the initial clearance was cancelled on December 22, 2024, rendering it inadmissible due to exceeding the 90-day statutory limit for delay condonation.
The environmental clearance, initially granted on November 18, 2022, to Vipin Kumar Saxena, was revoked by the State Level Environment Impact Assessment Authority due to significant non-compliance with its conditions. This non-compliance was confirmed by a joint committee report.